Tuesday, July 14, 2026
BCN.
Technology

New York becomes the first state to pause permits for data centers over 50 megawatts

Executive Order 62 holds state environmental permits for up to a year. The money is in the parts nobody is quoting.

Janet Torvalds

July 14, 2026

Governor Kathy Hochul signed Executive Order 62 on Tuesday, and it does one blunt thing: New York's Department of Environmental Conservation has to stop acting on permit applications for data centers that can draw 50 megawatts or more. The freeze holds until the Department of Public Service finishes a Generic Environmental Impact Statement covering data center construction and operation. The governor's office says that will take up to a year. No other state has done this statewide.

That is the version in the press release. The order itself is narrower and more interesting.

What the order actually freezes

The text directs DEC to "hold in abeyance" applications for any discretionary permit, approval, or license to build or expand a data center, with one condition attached: only applications that DEC had not already deemed complete before July 14. Anything ruled complete before Tuesday keeps moving. And the order says plainly that it "does not apply to permits, approvals, licenses, or similar forms of permission from local governments." Town planning and zoning boards keep their authority, and the press release confirms that once the standards land, projects proceed "as long as they follow state, zoning code and other local approvals."

The 50 MW line is a capacity test, not a meter reading. The definition covers facilities that "consume or can consume" 50 megawatts or more, in buildings with UPS systems and high-density cooling. Facilities used primarily for manufacturing, medical care, education, or research are carved out, and the carve-out names the Empire AI consortium by statute. Chip fabs and university clusters are not the target here.

Which leaves the question nobody has answered yet: how many projects in New York's pipeline actually need a discretionary DEC permit? A hyperscaler on an already zoned site, taking grid power, without a major air or water withdrawal permit, may not need one at all. The moratorium is real, but it is a hold on one specific gate, not a construction ban. CBS New York described the order as one that "bans state lawmakers from approving environmental permits," which is not what any part of this does.

The number driving it

The order's own findings carry the figure that explains the panic. As of May 2026, nearly 12 gigawatts of data center load requests sit in the New York Independent System Operator's interconnection queue, and more than eight gigawatts of that arrived in 2025 alone.

Queue requests are not projects. The order concedes as much, warning about utility investments "made in anticipation of loads that may not fully materialize," which is the polite phrasing for developers shopping the same speculative campus to five interconnection queues at once and leaving ratepayers holding a substation nobody needs. That risk, not water or noise, is what the money sections of this order are built around.

The parts that outlast the pause

The permitting freeze is temporary. The rest of EO 62 is the durable piece, and it comes with a clock.

DeadlineWhoWhat
60 daysEmpire State DevelopmentPublish a Community Investment Framework for localities negotiating with developers
60 daysDept. of Public ServiceStand up a Data Center Interconnection Working Group
90 daysDept. of Public ServiceReport to the Public Service Commission on how transmission owners study large-load system impacts
12 monthsDept. of Environmental ConservationReport on whether water withdrawal rules (6 NYCRR Parts 601 and 602) capture data center demand
Until the GEIS is finalDECHold new discretionary data center permits

Buried in section 3 is the one with actual money in it. DPS is told to consider a "New York Grid Acceleration Fund," under which data centers would make upfront capital contributions toward grid upgrades, join demand response programs, fund new clean generation and battery storage dedicated to their own load, and pay into an insurance pool against stranded assets. Cost allocation, not permitting, decides whether these campuses get built. A developer can wait out a one-year permit hold. A developer cannot wait out a rule that says you pay for your own transmission upgrade and post collateral in case you walk away.

All of it runs through the existing Energize NY large-load proceeding, Case 26-E-0045, which Hochul opened earlier this year on the principle that large consumers "pay their fair share or supply their own power."

Who is unhappy

The building trades, immediately. "A shortsighted moratorium only accomplishes one thing: it kills good-paying union jobs," said Mark McManus, general president of the United Association of Union Plumbers and Pipefitters, in a statement to CBS New York. "Rather than implementing guardrails to build the future of American ingenuity, Governor Hochul is taking her ball and going home."

Hochul's answer, posted to X on Tuesday: the state still wants AI investment, "but when you benefit from the talent and energy of New York, we expect you to protect our resources and give back to our communities." The Community Investment Framework is the specific answer to McManus. It tells ESD to write guidance that puts organized labor "a seat at the table" and prioritizes prevailing wage, project labor agreements, local hiring, and apprenticeships. Whether guidance a locality may use is worth more than permits a developer can pull is a fair thing for a union to be skeptical about.

Public opinion is running the other way from the trades. A Gallup survey in March found roughly seven in ten Americans oppose an AI data center in their own area, including 48 percent strongly opposed. Seattle, Minneapolis, and several New Jersey towns have already passed or floated local restrictions. New York is the first to do it at the state line.

What is still pending

Two things.

The legislature passed a tougher bill last month that Hochul has not acted on. It would set the threshold at 20 megawatts rather than 50, impose energy efficiency standards on anything above one megawatt, and require covered facilities to run almost entirely on renewable power by 2050. The executive order does not moot it. If she signs it, the 50 MW line in EO 62 becomes the floor rather than the rule.

She also said Tuesday she will pursue legislation repealing New York's sales tax exemptions for large data centers. That one is worth watching more than the moratorium is. Servers and cooling gear are the bulk of a hyperscale build's capital cost, and the exemption on them is a large part of why New York has been a candidate site at all.

Executive Order 62hyperscale data center permitsEnergy GridNew York data center moratoriumAI InfrastructureNYISO interconnection queueGrid Acceleration FundKathy Hochul data centersTech Policydata center regulationData centers

Keep reading